ECONOMYNEXT – Energy and forex crisis-riddled Sri Lanka will see yet another scheduled power outage on March 01, this time at a stretch of three hours between 8.30am and 5.30pm, with a possible unscheduled interruption of 30 minutes at night.
The Public Utilities Commission of Sri Lanka (PUCSL) said it has approved a request by the Ceylon Electricity Board (CEB) to go for the scheduled load shedding.
In A,B,C areas, power cuts of 2 hours will be imposed from 8.30am to 17.30pm .
Also in P,Q,R,S,T,U,V,W areas power cuts of 3 hours will be imposed from 8.30am to 17.30pm.
“In those areas 300 MW to be shed from areas in P,Q,R and U,V,W groups while 200 MW to be shed from areas in S, T groups,” the CEB said.
“It is to be noted that above schedule shall not be adequate to cater the required deficit and additional hydro generation shall be utilized to meet the demand.”
Download the March 01, power cut schedule here: 01-03-2022-Power-Interruption-Schedule
Owing to a crippling forex shortage in the country, the state-run Ceylon Petroleum Corporation (CPC) has failed to maintain a continuous supply of fuel to the CEB to run its thermal power plants, forcing the utility provider to go for power cuts, causing much inconvenience to the public.
Monday (28) saw the PUCSL approving power cuts that extended up to five hours and 15 minutes in many areas.
Analysts say the power cuts can extend till April- May depending on the fuel supply.
Due to the unavailability of fuel, the CEB said in a statement on Tuesday, the Kelanitissa power plant, the Kelanitissa combined cycle power station and the barge-based power plant at the Colombo port were all shut down while supplementary power stations in Mathugama, Thulhiriya, Kolonnawa were also unavailable due to lack of fuel.
According to the CEB, currently only the Sojitz and Uthuru Janani power plants have enough fuel to run for another 6.3 days and 8.1 days respectively.
The CEB said in order to supply the demand for March 01, the board needs 1,120 metric tons of furnace oil, 950 metric tons of naphtha and 2,640 metric tons of diesel. However, only 167 metric tons of furnace oil and 650 metric tons of diesel are in stock and no naphtha stocks are currently in store.
There is a deficit of 349 megawatts (MW) for the day peak, 479 MW for the evening peak and 49 MW for night peak for March 01.
Therefore, 100 MW will be shed as per the following schedule: from Kosgama, Seethawaka, Athurugiriya, Kegalle, Thulhiriya, Maliboda, Kurunegala, Pallekele, Kiribathkumbura, Ukuwela, New Galle, Balangoda, Deniyaya, Embilipitiya, Hambanthota, Rathnapura, Matara and Beliatta GSS. Refer annex 01 for feeder list. (Southern, Sabaragamuwa, Part of the Central, part of the North West and part of the Western provinces. (Colombo/Feb 28/2022)